Alberta Transportation has informed the Town construction between 51 Avenue and 55 Avenue will continue through to mid next week as part of the Highway 779 Construction Project.

Crews will be locating and hydrovacing the underground utilities in the back lanes on the east side of 48 Street between 52 Avenue and 56 Avenue on Saturday, August 8 and Monday, August 10. The alleys will remain open to traffic during construction, but access may be limited at times to accommodate hydrovac equipment. Concrete pouring for the new curb and gutter along the west side of 48 Street between 51 Avenue and 55 Avenue is scheduled for Tuesday, August 11. Paving of the road widening between 51 Avenue and 55 Avenue is scheduled for Thursday, August 13 and Friday, August 14.

Streetlight installation work along the west side of 48 Street between 57 Avenue and 55 Avenue will resume on Monday, August 10.