Golf Course Road Construction Update – August 6, 2021
Golf Course Road construction crews are now done ripping up the old road between Hwy 628 and the Fairways/Brightbank Intersection. Today through Sunday there will be minimal lane closures. Now that pulverizing is complete the next phase of the project will begin on Monday called foaming, a process of mixing oil and water with the pulverized material to create a new road structure. To complete this process traffic will be reduced to one lane with alternating directions once again.