| Crew 1 | Status | Crew 2 | Status |
| Fairways | Completed Jan 8 | Woodlands | Will continue January 13 |
| Ironwood | Completed Jan 10 | Folkstone, Brickyard, Old town | Old Town is in progress |
| Graybriar | In Progress | Southridge, Stony Creek & Creekside Point | |
| South Creek | Forest Green & Egerland Place | ||
| Country Plains Estates | Completed Jan 10 | Jutland Ridge & Sun Meadows | |
| High Park | Silverstone | ||
| Westerra Lakes | Brookview | ||
| Glens & Heritage Cres | Homesteads & Stone Haven | ||
| Genesis | Meridian Heights | ||
| Willow Park | St. Andrews |
Residential snow removal may occur once the snowpack reaches approximately 10 cm or when emergency access could be restricted. Timing also depends on conditions and operational priorities.
Not all neighbourhoods are serviced at the same time. The neighbourhood rotation order changes each year to ensure fairness. If a neighbourhood was last the previous year, it will now be first this year. Once this neighbourhood has had its turn being first its bumped down one spot each year.
Crews do their best to remove the snow and ice down to the pavement, but this may not always be possible due to weather and surface conditions.
In some cases, ice and snow may be pushed onto the sidewalk during residential snow removal. Property owners are responsible for clearing sidewalks after crews have been through the area.
Snow clearing will not occur on garbage days, schedules may be adjusted to accommodate garbage collection days.
In some areas, such as cul-de-sacs or corners, crews may need to make more than one pass to complete snow removal.
Remove vehicles prior to snow removal and do not return vehicles to the street until crews have completed snow removal and signs (if placed) have been removed.
Driveway ramps must be removed, as they can damage snow removal equipment and delay operations.