    Underground construction at the Central School site is now complete. Surface work will begin as soon as possible, weather dependent.

  • Downtown Redevelopment Update July 10

    Timelines for the Downtown Redevelopment project have been impacted by recent rain. At present, the project is behind the originally projected schedule.

  • Highway 779 Construction Update July 9

    Alberta Transportation (AT) has informed the Town that inclement weather has caused delays over the last two weeks. Despite the rain delays, work continues on the 48 Street (Highway 779) Grade Widening Project.

  • Downtown Redevelopment July 30 Update

    Phase IV of Downtown Redevelopment is progressing with the recent warm weather. Underground work at 51 Avenue has been completed and surface work is underway.

  • Highway 779 Construction Update July 28

    The Town has been informed that access to 50 Avenue at the intersection of 48 Street is currently closed for Alberta Transportation’s Highway 779 construction project. The intersection is scheduled to be paved and reopened to traffic by end of day Wednesday, July 29.

  • Highway 779 Construction Update June 25

    Alberta Transportation’s (AT) Highway 779 Project continues with grade widening between 57 Avenue and 55 Avenue. Curb and gutters are scheduled to be poured this Friday (June 26) and Saturday (June 27).

  • Highway 779 Construction Update June 18

    The Town has been informed by Alberta Transportation (AT) that both southbound lanes of 48 Street between 55 Avenue and 57 Avenue will be closed on Friday, June 19 to accommodate concrete pouring for the Highway 779 project. While lanes are closed, traffic will be shifted to the centre northbound lane and northbound traffic will be restricted to the outside lane only.

  • Downtown Redevelopment Update June 18

    Downtown Redevelopment is moving forward with the installation of the water main on the east side of 50 Avenue. Concrete work for the sidewalk west on 50 Avenue is now complete.

  • Highway 779 Construction Update June 15

    Alberta Transportation reopened the intersection of 48 Street (Hwy 779) and 57 Avenue at 7:00AM this morning. Detour signs in the area have been removed by construction crews.

  • 57 Avenue Intersection

    Alberta Transportation has informed the Town the opening of the 57th Avenue intersection has been delayed.


Contact Us

Town Office: 780 963 2151
Public Works: 780 963 2469
Email Us

Monday-Friday
8:30 AM to 4:30 PM

Public Works After Hours Emergency Line

780 818 6766

This website uses cookies to enhance usability and provide you with a more personal experience. By using this website, you agree to our use of cookies as explained in our Privacy Policy.