Alberta Transportation has provided the following important update to the construction on Highway 779. Today, crews will be placing mulch in the median, between 55 and 52 Avenue.
Foaming is done and manholes have been reset. Crews are now prepping for paving which will occur in the coming weeks.
Alberta Transportation has updated the Town on the Highway 779 construction project. The multi-use trail along 79 Avenue between Willow Way and 48 Street has been constructed and paved and is now open for use.
Microsurfacing in residential areas has been primarily completed. The contractor is currently repairing deficiencies in some areas.
Starting today, foaming will take place on Golf Course Road and continue until early next week. At that point, final paving will commence.
Road base work continues on the Downtown Redevelopment project. Curb, gutter and sidewalk forming is underway in conjunction with concrete pouring.
Golf Course Road construction crews are now done ripping up the old road between Hwy 628 and the Fairways/Brightbank Intersection. Today through Sunday there will be minimal lane closures.
Work continues on concrete replacement at the entrance of the alleyway behind The Old Bar. It remains closed; however, it is still on track to open for 6am August 11.
An update to the Highway 779 construction project has been provided by Alberta Transportation. The concrete crew will be machine pouring the median curb and gutter for the medians between 55 Ave and 49 Ave on today and tomorrow.
Contact Us
Town Office: 780 963 2151
Public Works: 780 963 2469
Email Us
Monday-Friday
8:30 AM to 4:30 PM
Public Works After Hours Emergency Line
STAY UP TO DATE
Subscribe for email notifications about announcements, news, events, programs, and more!